This sign will be in front of each house under construction

Here's the cleared lot with a tool trailer moved in.

22 Nov - The foundation work being done

27 Nov - Foundation is done and the slab is being formed up

4 Dec - The slab is curing awaiting the walls

6 Dec - The Southwest Technology Center Construction Trades class
has put up the first walls

9 Dec - Volunteer workers from the local area start putting
the exterior on. 
9 Dec - Everybody pitches in at the end of the first volunteer
building day

Ah Progress..... |